4. Way leave proposals: |
Sl. No. | Service | Time limit | Single Window Agency (to be contacted for progress/ non-compliance) |
4.1 | In principle approval of proposal of Divisions | 30 days | Khurda Division: Sr.DEN (Coordination) srdencokur@kur.railnet.gov.in WaltairDivision: Sr.DEN (Coordination) srdencowaltair@yahoo.com SambalpurDivision: ADRM adrm_sbp@sbp.railnet.gov.in |
4.2 (i) | Applications under Divisional Powers Not involving Track crossing | 45 days | Khurda Division: Sr.DEN (Coordination) srdencokur@kur.railnet.gov.in WaltairDivision: Sr.DEN (Coordination) srdencowaltair@yahoo.com SambalpurDivision: ADRM Adrm_sbp@sbp.railnet.gov.in |
4.2(ii) | Applications under Divisional Powers Involving track crossing | 60 days | Khurda Division: Sr.DEN (Coordination) srdencokur@kur.railnet.gov.in WaltairDivision: Sr.DEN (Coordination) srdencowaltair@yahoo.com SambalpurDivision: ADRM Adrm_sbp@sbp.railnet.gov.in |
4.3(i) | Applications under Headquarters Powers Not involving CRS sanction | 75 days | CGE cge@ecor.railnet.gov.in |
4.3(ii) | Applications under Headquarters Powers Involving CRS sanction | 105 days. | CGE cge@ecor.railnet.gov.in |