1.0 Opening of New Private Sidings/Private Freight Terminals (PFT): (Greenfield projects) (When consultant is engaged) |
Sl. No. | Service | Time limit | Single Window Agency & reference Circular |
1.1 | In Principle approval | 35 working days from the date of application along with non refundable deposit of Rs. 20,000 (in the form of DD to FA&CAO/ BBS) | CTPM(ctpmecor@gmail.com) Refer to FM Circular 11 of 2016& corrigendum as applicable from time to time |
1.2 | Detailed Project Report (DPR) approval | *Within 85 working days from the date of submission. | CTPM(ctpmecor@gmail.com) Refer to FM Circular 11 of 2016& corrigendum as applicable from time to time |
1.3 | Divisional certification after execution of the works | 30 days | Sr.DOM of concerned Division srdom_wat@wat.railnet.gov.in srdom_sbp@sbp.railnet.gov.in sr.dom-kur@kur.railnet.gov.in |
1.4 | Private Siding | | CCM/FS (ccmfs@ecor.railnet.gov.in) |
1.5 | Private Freight Terminals | i) IPA-45 days form the date of submission of application along with fees of 10 lakhs. ii) DPR approval one month from date of submission(Green filed & for Brown field). | CTPM (ctpmecor@gmail.com) Refer to PFT Master Circular 2015/0 & corrigendum as applicable from time to time |
| | | |
*Subject to submission of application for IPA and DPR as per check list and compliance of all observations by Railway promptly.
For details please visit official web site of Indian Railways
Disclaimer:
Above time limits for delivery of services does not confer any right on citizens/Customers for legally questioning Railways when there is some failure to deliver services within the prescribe time limits.