System Improvements Suggested by ECoR Vigilance Department in Year 2020:

Serial No

Department

System Improvement suggested

Implementation Status

2020/01

Commercial

RCT claim case under section 124(A)

Implemented

2020/02

Commercial

Irregularities in claim settlement cases under section 124-A of Railway’s Act 1989

Implemented

2020/03

Engineering

Guarantee and penalty clause in contracts for distempering and exterior painting of service building and Quarters

Implemented

2020/04

Accounts

Implementation of Quarter Modulein IPAS

Implemented

2020/05

Accounts

Improvement in IPAS module

Yet to be implemented

2020/06

Commercial

Introduction of Q-system for occupation of seats in unreserved coaches of in-demand originating trains

Implemented

2020/07

Personnel

System improvements in regard to affixing travel entitlement Stamp o­n passes

Implemented

2020/08

S&T

Minor alterations in Electronic Interlocking

Implemented

2020/09

S&T

Maintenance of selected EI stations departmentally

Implemented

2020/10

Mechanical

AEBAS at Workshops should be coupled with access gates so that no Workshop staff can pass through main entrance without punching of his movement

Partially implemented

2020/11

Engineering

Disposal of unserviceable PSC sleepers

Implemented

2020/12

Stores

Warranty clause for materials other than M&P should be more specific o­n time line for rectification/replacement, place of rectification and penalty for delay in attending.

Yet to be implemented

2020/13

Personnel

Grant of Personal Computer Advance.

Implemented

2020/14

Engineering

Transportation of P.Way materials

Yet to be implemented

2020/15

Mechanical

Development of in-house maintenance facilities for Disc mounted Air Brake system of LHB couches in graduated and time bound manner.

Yet to be implemented

2020/16

Engineering

Guidelines in case of consumption of cement more than CVC guidelines and nodal Sr DEN in case work is executed two Sr DENs.

Yet to be implemented

2020/17

Engineering

Plantation of saplings through agencies

Implemented

2020/18

All

Procurement through third party inspection

Implemented

2020/19

All

Action to be taken for payment to contractual staff by contractors

Yet to be implemented

2020/20

Electrical

Provision of metering units at sub-stations of domestic electric supply

Implemented

2020/21

All

To ensure authentic and valid RDSO/RITES Inspection certificate

Yet to be implemented




Source : East Coast Railway CMS Team Last Reviewed : 18-04-2022  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.