4. Way leave proposals:

Sl. No.

Service

Time limit 

Single Window Agency
(to be contacted for progress/ non-compliance)

4.1

In principle approval of proposal of Divisions

30 days

Khurda Division: Sr.DEN (Coordination)

srdencokur@kur.railnet.gov.in

WaltairDivision: Sr.DEN (Coordination)

srdencowaltair@yahoo.com

SambalpurDivision: ADRM

adrm_sbp@sbp.railnet.gov.in

4.2 (i)

Applications under Divisional Powers

Not involving Track crossing

45 days

Khurda Division: Sr.DEN (Coordination)

srdencokur@kur.railnet.gov.in

WaltairDivision: Sr.DEN (Coordination)

srdencowaltair@yahoo.com

SambalpurDivision: ADRM

Adrm_sbp@sbp.railnet.gov.in

 

4.2(ii)

Applications under Divisional Powers

 Involving track crossing

60 days

Khurda Division: Sr.DEN (Coordination)

srdencokur@kur.railnet.gov.in

WaltairDivision: Sr.DEN (Coordination)

srdencowaltair@yahoo.com

SambalpurDivision: ADRM

Adrm_sbp@sbp.railnet.gov.in

 

4.3(i)

Applications under Headquarters Powers Not involving CRS sanction

75 days  

CGE
cge@ecor.railnet.gov.in

4.3(ii)

Applications under Headquarters Powers Involving CRS sanction

 105 days.

CGE
cge@ecor.railnet.gov.in




Source : East Coast Railway CMS Team Last Reviewed on: 28-09-2016